Quantum meruit literally means ‘what the job is worth’. Where an owner has received a benefit from the contractor in unfair circumstances, or in other words has been unjustly enriched, equity in the form of quantum meruit, will intervene so that a contractor can claim a fair and reasonable sum for work performed and materials supplied.

When can a claim on a quantum meruit arise?

A quantum meruit claim may arise in various circumstances, including where:

  • work has been performed on the basis that a contract will be agreed, but where no contract is entered into;
  • a contract to perform work exists between parties, but a contract price is not specified;
  • a contractor performs work outside the scope of a contract, at the owner’s request and where the work is not captured by the contractual right to order variations;
  • a contractor performs work under a mistake and the owner knowingly accepts the work;
  • a contractor performs work under a contract that is void, unenforceable or terminated, including where a contract is terminated due to repudiation by an owner; and
  • Termination due to an owner’s repudiation.

Where a contract is terminated due to an owner’s repudiation, both parties are discharged from further performance of the contract. This is problematic for a contractor if a contractual right to payment has not yet accrued for works performed by the contractor before and up until termination. This is known as a total failure of consideration, and is the basis for a contractor’s claim in quantum meruit.

Refer to more articles:  What Is Asian Fit Eyeglasses

This can occur in the following scenarios:

  • Entire Contract – Where a contract consists of one whole obligation to perform works, a contractual right to payment will only arise upon completion of all of the works. If termination occurs before completion, there will be a total failure of consideration of the entire contract.
  • Divisible Contract – Where a contract comprises of divisible obligations, a contractor’s right to payment will arise upon completion of each of the divisible portions. Where repudiation occurs before completion of a divisible portion, there will be a total failure of a severable part of the consideration, given that this will result in incomplete works, in respect of that divisible portion.

In both of the above circumstances, the failure of consideration results in the contractor not being able to receive payment for the value of the works performed. This is because, upon termination, further obligations (including the obligation to pay) under the contract are discharged before the contractor’s right to payment for the work performed arises. Practically speaking, the owner receives value without being required to attend to payment in return, and is ‘unjustly enriched’. Accordingly, restitution in the form of quantum meruit is available for the contractor to claim.

Where a contract is terminated due to an owner’s repudiation, rights and obligations which have accrued under the contract up until the date of termination are unaffected. Where works are completed before termination (either wholly under an entire contract or in respect of a divisible portion under a divisible contract) a contractual right to payment will have accrued before termination given that it would have been triggered on completion. In these circumstances, quantum meruit is not available. A contractor’s remedy following termination is restricted to a claim in debt for the amount due that has accrued, or damages for breach of contract

Refer to more articles:  What Do White Ants Look Like

What is a reasonable sum?

The courts take several factors into account in order to calculate the quantum of a fair and reasonable sum. These may include:

  • the commercial rate for the work;
  • site conditions;
  • whether the contract refers to certain prices or formulas (having regard to the overall contract price);
  • conduct of parties; and
  • quality of work.

Given that quantum meruit is underpinned by unjust enrichment, the overall amount awarded will often depend on what is just in the circumstances. This may mean that the contractor may be awarded the full value of the work, only their costs, or in some circumstances, nothing at all.

The quantum awarded cannot exceed the overall contract price, unless circumstances dictate that it would be unconscionable to confine the contractor’s claim in this manner.

Related Posts

What Is Cpi Training For Special Education

We take a look at what CPI is and why it is so beneficial for de-escalating crises for children with autism in combination with several ABA strategies.You…

What Is 1 15 As A Decimal

Converting 1/15 to a decimal is quite possibly one of the easiest calculations you can make. In this (very short) guide, we’ll show you how to turn…

What Is Coryxkenshin Net Worth

What Is Coryxkenshin Net Worth

You may be interested What To Do In Holden Beach What Is A Perimeter Fence What Is The Reason That Motorist Don’t Stop What Is The Z…

What Time Is 22 45

Convert 2245 military time into standard (regular) AM/PM format. You may be interested What Is 13.1 What Does Riri Mean What Time Is 18 52 What Happened…

What Do Dental Implants Look Like

With changing technology, dental implants have become a go-to alternative to some other procedures. Dental implants work by replacing missing teeth as well as keeping prosthetics, like…

What Channel Is Cbs Uverse

Are you a fan of CBS shows and wondering if you can access them on AT&T? Well, you’re in luck! AT&T offers an exciting lineup of CBS…